Local Representatives Make Nearly 50 Visits to Infrastructure Office Over Delayed Chowkidanda–Olani Road; When Will Construction Be Completed?

२०८३ मंसिर ९, ०४:२५ Dineshkhabar Desk

Dhangadhi:How many times would local representatives have to visit a government office to get a road constructed? Once, twice, or perhaps ten times? In the case of the Chowkidanda–Olani road in Kailali, local representatives have visited the Infrastructure Development Office nearly 50 times. Yet, the condition of the road remains unchanged. Construction is still incomplete, and there has been little improvement in the contractor's pace of work.

Construction of the road, which began with blacktopping six years ago, remains unfinished despite repeated requests, pressure and protests. Last year, local representatives even operated a ward office on the road itself to protest the contractor's delays. Following the protest, a written commitment was secured in the presence of the local administration to complete the construction. However, with the commitment remaining unfulfilled, representatives have once again been forced to approach government offices with the same grievances.

On September 8, 2025 (Bhadra 23, 2082), the construction company signed an agreement in the presence of then Chief District Officer Krishna Prasad Lamsal to complete the work by the end of Poush. However, the deadline has passed without the road being completed. In response, ward chairpersons from Wards 3, 10, 11 and 12 of Godawari Municipality have once again visited the Infrastructure Development Office.

Ward No. 12 Chairperson Bhim Bahadur Khadka said repeated visits to the office have become embarrassing. According to him, representatives have visited the office around 50 times solely over the road construction issue. However, they have received little beyond repeated assurances.

"It feels as though we are visiting a court to check hearing dates. Being elected representatives and having to go through this repeatedly has become embarrassing. We are even reluctant to say that we have come here for the road when asked why we are visiting. We have already come around 50 times over this very issue. It has become humiliating," Khadka said.

Local representatives and residents had previously staged several protests demanding the speedy completion of the road. However, the demonstrations failed to accelerate construction. With even the agreement made in the presence of the administration remaining unimplemented, Khadka said they may have no option but to launch another protest.

He said the construction company had assured them that work would resume after Tihar, but no significant progress has been made so far. Concerned that the contractor may again suspend work citing the onset of winter, low temperatures or unfavourable weather conditions, local representatives have started approaching the office in advance.

"They had promised to resume work after Tihar, but it has still not started. Now winter has arrived, and we are concerned that they may again delay the work by citing cold weather, insufficient temperatures and other excuses. If the work does not move forward this time either, we will have no alternative but to protest," Khadka said.

The Chowkidanda–Olani road project was divided into two separate contracts. However, both sections are facing similar delays. Despite repeated extensions of construction deadlines, neither section has been fully blacktopped.

On August 8, 2020 (Shrawan 24, 2077), Adventure, Thegim and Sunlight JV secured a contract to blacktop a 2.5-kilometre stretch from Krishna Temple in Chowkidanda to the office of Ward No. 10 of Godawari Municipality. Although the agreement required the work to be completed within one and a half years, construction on the section remains incomplete.

Similarly, another contract was awarded for blacktopping an additional three-kilometre stretch from the Ward No. 10 office to Bangesal. The contract, worth more than Rs 66.14 million, also failed to meet its stipulated deadline.

Tedi Nirman Sewa, which secured the second contract, had agreed to hand over the completed road by Poush 30. However, even the work of laying the base course over the sub-base remains pending.

The Infrastructure Development Office has also expressed dissatisfaction with the contractor's delays. According to the office, both contracts could have been completed by Chaitra had the construction companies worked regularly.

The Public Accounts Committee of the Provincial Assembly had also inspected the road and directed the concerned authorities to ensure the speedy completion of construction. However, neither the committee's directive, repeated pressure from the office nor protests by local residents have been enough to compel the contractors to accelerate the work.

According to Sangeet Rokaya, chief of the Infrastructure Development Office in Dhangadhi and a Senior Divisional Engineer, physical progress on the road construction remains extremely poor.

With the original contract periods having expired, the projects are currently operating under an additional 200-day period known as the Liquidated Damages (LD) period. The office is preparing to initiate the process of terminating the contracts if construction is not completed within this extended period.

"I have not been here for very long, but there has been little visible physical progress. The contract deadlines have expired, and the projects are currently in the 200-day LD period. If the work is not completed within this period either, we will move ahead with the process of terminating the contracts," Rokaya said.

The approximately 16-kilometre road from Chowkidanda to Bandrekhal is planned to be extended to Phaltude and connected to the Mahakali Highway. The road is expected to connect settlements in the hilly areas of Godawari to the road network and significantly improve local transportation, accessibility and development.

However, with construction dragging on for years despite repeated assurances, inspections and protests, residents and local representatives are still waiting for one answer: When will the Chowkidanda–Olani road finally be completed?

 